• DSC 0319 640x360
    Building yard equipment: The contractor proofs his competence on the parking
  • DSC 0334 640x428
    Works start at the first spur
  • DSC 0330 640x428
    We only bought best materials following EC standards, as our projectcoodinator M. Metaga Traoré could assure himself on the building site.
  • DSC 0342 640x428
    The waterway construction matrasses are filled with locally available blocs from laterite material
  • DSC 0339 640x428
    Hawua Coulibaly from ONF and Dr. Koch with a plant arriving from the nursery
  • DSC 0346 640x428
    The matrasses are closed and fixed with a double torsion
  • DSC 0348 640x428
    The plants are placed between the rocks and interstices are sluiced with a liquid soil water mixture
  • DSC00402 640x480
    The last and largest spur just before completion
  • DSC00417 640x480
    Fofana, focal point of the ONF for our project, explaining the project to local representatives
  • DSC00390 640x480
    One of the smaller spurs readily planted. Unfortunately most of the plants are belonging to Sesbania pachycarpa (annual) instead of the ordered Sesbania sesban
  • PB260033 640x480
    February 2014, the site is reappearing after its first inundation season. At this moment most of the plantes look dead
  • PB260049 640x480
    But there is life on the spurs
  • PB260049 640x423
    Fry is well camouflaged on the sediment. They have use the wires and the vegetation to hide to hide during the inundation
  • PC060033 640x480
    One fortnight later the plants show first fresh leafs